Week 4 Gantt Chart Critical Path and Assignment

Week 4 Gantt Chart Critical Path and Assignment
Stadium Builders RS are preparing a bid to build a new 75,000 seat baseball stadium in Delaware. The construction must start on June 1, 2021 and be completed in time for the 2024 season. A penalty clause of $90,000 per day of delay beyond April 20, 2024 is written into the contract.
Willie Robertson, the president of the company could net as much as $1.9MM on the project. He also said if they are successful, the prospects for future projects are very good since there is a projected interest in building new ball parks with modern luxury boxes.
Given the information provided below for the stadium project, answer the following questions:
1. Will the project be completed by the April 20th deadline?
2. How long will it take?
3. What is the critical path for the project? (Highlight this on your Gantt chart if possible)
4. Based on the schedule, would you recommend that the new owner pursue this construction contract? Why or Why not?
5. Include a one page Gantt chart for the stadium schedule.
ID Activity Duration Predecessor(s)
1 Baseball Stadium
2 Get permits 10 days —
3 Clear stadium site 70 days —
4 Demolish building 30 days 3
5 Set up construction site 70 days 4
6 Drive support piling 120 days 3
7 Pour lower concrete bowl 120 days 6
8 Pour main concourse 120 days 4,7
9 Install playing field 90 days 4,7
10 Construct upper steel bowl 120 days 4,7
11 Install seats 140 days 8, 10
12 Build luxury boxes 90 days 8, 10
13 Install Jumbotron 30 days 8, 10
14 Stadium infrastructure 120 days 8, 10
15 Construct steel canopy 75 days 11

16 Light installation 30 days 15
17 Build roof supports 90 days 7
18 Construct roof 180 days 17
19 Install roof tracks 90 days 17
20 Install roof 90 days 18, 19
21 Inspection 20 days 9,12,14,16,20

-Study Notes-
The project will not be completed by the April 20th deadline as the final inspection is scheduled on Day 21 and that is after April 20th.

The project will take at least 691 days (from Day 1 until Inspection day).

The critical path for the project is:

ID 3 “Clear stadium site”
ID 6 “Drive support piling”
ID 7 “Pour lower concrete bowl”
ID 8 “Pour main concourse”
ID 9 “Install playing field”
ID 10 “Construct upper steel bowl”
ID 11 “Install seats”
ID 15 “Construct steel canopy”
ID 17 “Build roof supports”
ID 18 “Construct roof”
ID 19 “Install roof tracks”
ID 20 “Install roof”
ID 21 “Inspection”
Based on the schedule, I would not recommend that the new owner pursue this construction contract. The project is not completed by the April 20th deadline and also the penalty clause of $90,000 per day of delay beyond April 20, 2024.

Tags: ,

Find The Best Writers, Tutors & Assignment Writing Experts!

2025 Special Offer! Get 20-25% Off On ALL Your Orders!

Why trust us?

Every student wants the best grades and that’s our Focus

Graduate Level Writers

Our team consists of outstanding writers who have specialized knowledge in specific subject areas and professionals experienced in academic research writing. They hold at least a graduate degree—230 with Masters and MSN, experts carefully selected and trained to ensure the best quality of our work. .

Discounted Prices

We are committed to hiring the most skilled writers who can deliver high-quality work at a reasonable price for college students. Thus, we offer the best value for money without sacrificing the standard of our essay writing services; the quality of the paper's content. #Remember to activate the DISCOUNT Code on the order form COUPONS' section before making payment for your essay.

100% Plagiarism-Free

The service guarantees that our final work is 100% original, rearched and human written. We are committed to delivering plagiarism-free and AI-free work to each university/college student's 'write my paper' request. To uphold this promise, we check every draft for any possible instances of duplication, wrong citation, grammar errors and artificiality before we send it to you. Thus, you can always rely on us to write genuine and high-standard content for your essay assignments.

How it works

When you decide to place an order with Homework Ace Tutors, here is what happens:

Complete the Order Form

You will complete our order form, filling in all of the fields and giving us as much detail as possible.

Assignment of Writer

We analyze your order and match it with a writer who has the unique qualifications to complete it, and he begins from scratch.

Order in Production and Delivered

You and,the support and your writer communicate directly during the process, and, once you receive the final draft, you either approve it or ask for revisions.

Giving us Feedback (and other options)

We want to know how your experience went. You can read other clients’ testimonials too. And among many options, you can choose a favorite writer.

Write My Essay For Me